Implementing Program Support in Project Server 2010 - Part 2

In this post, I will cover how the Program  support can be enabled using another product from FluentPro products portfolio - FluentPro Autocomplete Manager.

Autocomplete manager allows to enable auto complete feature to project level custom text field and get the data from 3 data sources:
- SQL Server Query
- SharePoint List
- Project Server Security Group

So, let's start.

I assume that Autocomplete Manager is installed and licensed.

1. Create 3 fields:

  • Portfolio Name - project level, Text, Single line
  • Program Name - project level, Text, Single line
  • IsProgram - project level, Flag



2. Add these 3 fields to Project Information PDP


3. Create 2 projects, Program A, Program B and "check" IsProgram field.


4. Create new SharePoint List in PWA and call it Corporate Portfolio. Add 3 items - Portfolio A, Portfolio B, Portfolio C


5. Got to Server Settings -> Project Detail Pages and open Project Information PDP for edit.
next to Program name and Portfolio Name fields you will see icon - that's icon for Autocomplete Manager settings for that field.


6. Click on first icon (next to Program Name). We want to configure this field to pick values from Reporting Database for this PWA so we can build a list of projects that are "programs" (have IsProgram = 1). Fill the data as shown here (please note that you might need to provide credentials / get access to DB. Talk to your DB Admin):



You can test both connection string and SQL Query for errors in run time by clicking on Test buttons.

7. Let's configure Portfolio Name field to get data from SharePoint List we created:


8. We should be all set. Let's save changes to PDP, go to Project Center and create new project.
Start typing in Program Name field - Autocomplete Manager will provide all options that match:


Start typing in Portfolio Name field - Autocomplete Manager will provide all options that match:


That's it. In case of using Autocomplete Manager, your system is very dynamic, no server side jobs needed. Very easy to use.

Summary:
Both approaches have cons and pros. If you prefer to use Lookup Tables - then you can use Lookup Manager. If you are fine with content from data source directly and good to go with values in text fields only - Autocomplete Manager provides the most easiest way .


Note 1: We covered using Autocomplete Manager for SharePoint Lists and SQL Server. In Addition, it allows to use it as "People Picker" picking data from Project Server User Groups.

Note 2: Versions of Lookup Manager 2013 and Autocomplete Manager 2013  for Project Server 2013 are expected around mid-February.


Let us know if you have any questions - we would be happy to answer all of them.

Implementing Program Support in Project Server 2010

Many organizations that have a more than average number of projects, usually are grouping projects into programs and portfolios. In this post and next one I will describe the best ways how to enable support of "Programs" in Project Server 2010 and how our products can help.

Out-of-the-box solution - Master Projects / Sub Projects

In Project Server by default there is no concept of "Program", but project sever supports the so called "master project" / "subproject" functionality. That means, that users can insert projects into one project (usually a "container" project) and that project can become master project and a "program".

This approach has multiple advantages and disadvantages (you can see everything in one place but the same time there are multiple challenges with edit / read-only, it is very hard to deal with projects that contain tens of subprojects).

Several blog posts:



You can search in Google /Bing for more information using the keywords "master project subproject project server 2010" and will find additional information.

Custom solution - Using Custom Fields

Another approach is to create one field with lookup table - Program Name and use it as selection / dropdown for selecting programs from that dropdown.

There is one big disadvantage of this approach - user needs to support content of that lookup table manually, but with small number of programs this works better and is a more "cleaner" solution.

FluentPro has 2 products that can help with this :


In this post, we will create overview for implementing this approach with help of one of our products - Lookup Manager, product that allows sync of custom lookup table with data from SharePoint list or any database.

We will create 1 lookup table and 2 fields:

Lookup table:

      Program

Fields:

  • IsProgram (Flag, project level)
  • Program (Text, project level, referencing Program lookup table).

we will add both fields (IsProgram and Program) to Project Information PDP.

As next step, we will configure installed Lookup Manager to read data from Reporting Database. We want to select all project names that are programs (have IsProgram set to 1 (Yes)) and add them to than lookup table.

1. Go to Site Actions -> View All site Content and click on the list"FluentPro Lookup Manager".

2. Go to Items -> New item -> SQL Data Source. That will open window where you need to define a sync rule.


3. Enter all information and press Save button. This will create a SharePoint job, and you can adjust schedule to work as you want.  Please use information from your project server configuration (server name, database name):



4. For this scenario, we will set it to work every 5 minutes - it means, system will query database every 5 minutes and if required will try to update lookup table with values.
- Go to Central Administration -> Monitoring -> Timer Jobs -> Review Timer Job Definitions.

- Find job with name: LookupSynchronizationJob/<pwaname>  and click on it
- Change schedule and click OK.


5. Let's create 2 projects that are programs: Program A and Program B (do not forget to set IsProgram field).

6. Wait for 5 minutes and start creation of new projects - and check values in dropdown for Program field:


That's it. If you do not create programs very often, you can set the job to run once a day or on any desired schedule.

Few more features of FluentPro Lookup Manager:

- Data can be synchronized from SQL Server as well as SharePoint data sources.
- We support multi-level lookup tables (data in source should use the separator for each element: Level1.Level2.Level3) Any number of hierarchy levels is supported and separator is configurable.
- Lookup Manager is not deleting elements, only adding new ones

In next post, we will describe how to implement support of programs using Autocomplete Manager.

Looking for several companies / consultants to test FluentPro Project Migrator - bulk MPP migration software for Project Server 2010

We've completed development cycle and are very close to complete internal testing cycle for FluentPro Project Migrator software that allows to migrate projects (MPP files) from other EPM systems (Attask, Daptiv, EPM Live - any system that can save to MPP) and from any Project Server 2010 PWA instance (in case of PWA - we support project-level and task-level metadata migration as well) into Project Server 2010 PWA.

We are looking for 5 to 10 companies to be a first beta-testing users. In return for the participation in test and feedback, you will receive one license at no cost right after public release (March 2012 at Microsoft Project Conference 2012 ).

Product is implemented as add-in for Project Professional 2010.

Please send your contacts to beta (at) fluentpro.com with potential problem / task that you have and after review we will send you copy of software installation package and links to several video on how to use the software.

We plan to distribute version on March 1, 2012. There will be 2 versions - Lite with some limitations and Pro without any limitations. Product will be distributed independently and as part of FluentBooks Pro package.

Preview video is available here:

Getting Started with Project Server 2010 - Part 1 - Post Installation Steps

This video demonstrates some recommended post-installation activities to start the use of Microsoft Project Server 2010:

  • Configuration of Enterprise Calendar
  • Custom Fields
  • Notifications
  • Security for Project Delete
  • Time tracking configurations and Time Periods
  • Configuration of Administrative Backup.





Part 2: http://www.projectserverblog.com/2012/01/getting-started-with-project-server_15.html

Note: You might want to install the free edition of our Project Server 2010 Configuration Audit Software - FluentPro Audit Lite. It is absolutely free to use and easy to install.

2 more product videos available - FluentPro Publisher and FluentPro View Manager for Project Server 2010

Today, we've prepared 2 more videos for our products:


  • FluentPro Project Publisher - software that allows to re-save and re-publish all or selected projects

  • FluentPro View Manager - this is an update (v.2.0) of our existing product that allows to customize Project Server 2010 and link views to EPT and user security group membership and define default views to load. 


FluentPro Project Publisher





FluentPro View Manager



Enjoy - and we would be happy to hear your feedback!